Steel girder completion ng Skyway Extension umusod sa Feb. 2021

Steel girder completion ng Skyway Extension umusod sa Feb. 2021

November 21, 2020 @ 4:53 PM 1 week ago

  •  
  •  
  •  

Manila, Philippines – Tinatayang aabutin pa ng Pebrero 2021 ang 10-billion Skyway Extension project mula Susana Heights, Muntinlupa patungong Sucat, Parañaque makaraang magkaaberya kanina na ikinasawi ng isa.

“The girder fell on vehicles below, killing at least one and injuring at least four persons who were rushed by ambulances from the Skyway O&M Corp. and EEI to various hospitals,” lahad ng project contractor EEI Corp.

“This unfortunate incident sets back the completion of the Skyway Extension project,” hatol ng San Miguel Corp.

“From the December 2020 deadline, target completion is now February 2021.”

Ang naturang proyekto ay susi umano upang mabawasan ang trapiko sa southern Metro Manila partikular na sa South Luzon Expressway (SLEx) at Alabang area.

“We deeply regret this unfortunate accident and assure a full and thorough investigation. Our thoughts and concern are with the victims and we will make sure they will get all the help they need. Their welfare is our priority,” lahad pa ng SMC. RNT/FGDC


  •  
  •  
  •  